Construction Lien Rights: How Liens Work, Who Has Them, and How to Protect Payments

Lien and Payment Rights

In reality, most projects don’t start with a lien problem. They start with a payment delay, a pricing dispute, or a breakdown in communication. But if those issues are not properly addressed, lien rights are often the next step. 

Understanding who has lien rights, how they interact with contractual payment rights, and how they affect project stability is essential for anyone managing construction work. 

This article breaks down how liens operate and what you can do to reduce disruption before it starts. 

What are Lien Rights? 

Lien rights are a unique tool for construction-related work being done on privately owned property. If you do work on a construction project that results in the permanent improvement of real property, you may well have lien rights. This generally refers to physical work done at the project site, though many states also provide lien rights to those doing design work. Note also that material suppliers and equipment renters generally have lien rights if their supplies or equipment are used in the permanent improvement of real property. 

The right to file a lien is the right to stake a claim in the property title or deed. When a lien is filed, the lienor is stating that they have not been paid and that, as a result, the title to the project property is clouded and unclear. If the lien is not resolved, the claimant ultimately has the right to file a lawsuit to enforce that lien, which could result in the forced sale of the property, called a mechanics lien foreclosure. Lien foreclosures rarely happen, but they speak to the ultimate power of lien rights.  

It’s also important to note that lien rights extend far down the payment chain. For instance, if a general contractor hires a subcontractor, and if that subcontractor hires another subcontractor – that sub-subcontractor will often be entitled to lien rights. The same is true for suppliers and equipment renters hired by contractors and subcontractors. A party far removed from the architect or owner running the project could ultimately throw a major wrench in the project. 

Note that for work done on public property, a payment bond claim offers similar protection: See What is a Payment Bond Claim and How Do You Make One? 

Payment Rights 

The right to be paid for your work is supported by a variety of rights, including lien rights. When hired to perform work, the terms of the contract (or the equivalent) establish the right to be paid for the work. As a result, failure to pay for the work could result in a claim for breach of contract. Other claims could come into play as well, like prompt payment claims, retainage law claims, conversion claims, etc. 

How do Liens Create Problems on Projects?  

Construction liens serve as a payment distress signal on a project, and they affect everyone in a few different ways. 

Liens cloud the title on the project property. In effect, they create a potential ownership dispute upon the land where work is being done. When a lien is filed against the property, that lien will show up in title searches as an encumbrance, which lenders, title companies, and prospective owners or investors will want cleared up immediately. In fact, for projects where lenders are involved, the lender will often refuse to release draws until any liens are cleared up. 

Liens create more practical issues as well.  

For one, a freeze or delay on payments can stop work at the project site or lead to delays in material or equipment delays. If not getting paid on one job, contractors and subcontractors might send their crew somewhere else, so scheduling and sequencing could create additional issues.  

For another, liens are often the precursor to lawsuits. Lien claimants may “enforce” or “foreclose” their lien by filing a lawsuit and could include additional claims, like breach of contract. Naturally, adverse parties in a lawsuit don’t always work harmoniously, and tensions could create more on-the-ground issues.  

Finally, in some cases, liens could lead to double payment. While some states have laws on the books protecting against this, others don’t. Here’s an example: A GC fully pays their subcontractor. That subcontractor is going out of business, and they fail to pay their supplier. That supplier files a lien. Work needs to continue, but the owner wants the lien resolved now and the bank won’t release any additional funding. Who’s going to pay? The GC might try and recoup some of that payment to their subcontractor, but in practice, recovery is often unlikely. For an immediate fix, the GC might pay the supplier to get the project going again. Or, maybe the owner will step in and go after the subcontractor later. Either way – someone has paid twice, and that’s eating into their margin. 

For more on the mechanics of lien filing: See Protection and Enforcement of Lien Rights 

How do Construction Liens Affect Payment Rights? 

Simply put, construction liens may be the most direct tool for forcing payment. A lien claimant can draft and record their lien at relatively low cost, making it  a lot easier to file than a lawsuit. Therefore, lien claims can have an outsized impact. 

Also, when filing a lien, the claimant creates headaches far beyond the party who hired them. Filing a breach claim or another nonpayment claim will typically pit a claimant against the party who directly hired them. But by filing a lien, the claimant brings others into the dispute: the party who hired the claimant, the owner, the lender, and even the architect may all have a hand in resolving the dispute. This means there’s less of a tendency for these third parties to treat the issue as someone else’s obligation.

Similarly, those third parties will put extra pressure on whoever is directly involved in the dispute. When the top of the payment and ownership chain are breathing down someone’s neck, they’ll be motivated to come to the table and resolve the dispute. 

How do you Avoid Construction Lien Filings? 

Owners, lenders, GCs, and architects should all be invested in preventing liens before they are filed. As mentioned above, these parties will often require lien waivers from everyone working on the project in conjunction with their pay app submissions. This is great for construction payment hygiene, but it’s not the first step. 

First, it’s a good idea to chart out every contractor, subcontractor, supplier, and equipment vendor who’s on the project. Depending on the complexity, this may take quite a bit of effort – but it’s worth it. What’s more, this list is invaluable when deciding who lien waivers will need to be collected from. And finally, if someone does refuse to submit a waiver, or if you receive a lien threat, having a quick reference guide will help to understand who that party is, what work they’re doing, who they’re doing the work for, and likely – why there’s an issue.  

But regardless of the above, requiring and collecting conditional lien waivers with payment applications provides a security blanket. Those reviewing the pay apps know that, as long as payment is made, those lien waivers will automatically kick into gear. And if someone threatens a lien after getting paid, it’s easy to point to that lien waiver as evidence that payment was properly distributed and the claim is baseless. If the claimant files their lien anyway, the waiver (coupled with proof of payment) will be worth its weight in gold. 

Using the Right Lien Waiver Templates 

A lien waiver process should not be improvised. Every construction business should adopt a lien waiver policy that defines: 

  • Which approved templates the company will use 
  • Who is authorized to review and sign waivers 
  • How payment verification is documented 
  • Where executed waivers are stored and tracked 
  • When, if ever, deviations from standard forms are allowed 

As we frequently hear from clients, standardization reduces risk. The fewer variations in your waiver language and approval process, the fewer opportunities for error. 

For a deep dive on lien waivers, see: Lien Waivers and Releases: A Practical Guide to Managing Payment Risk

AIA Contract Documents publishes state-specific and generic lien waiver and release forms designed to align with applicable requirements and common industry practice. Selecting a consistent, vetted template – and building your internal policy around it – helps bring discipline to the payment process. 

AIA Contract Documents has provided this article for general informational purposes only. The information provided is not legal opinion or legal advice and does not create an attorney-client relationship of any kind. This article is also not intended to provide guidance as to how project parties should interpret their specific contracts or resolve contract disputes, as those decisions will need to be made in consultation with legal counsel, insurance counsel, and other professionals, and based upon a multitude of factors.