By Sara M. Bour, Esq., Manager and Counsel, AIA Contract Documents
Access the G703®–1992, A201®–2017
To purchase a one-time use license for the documents in this article, visit the links below:
G703®-1992, Continuation Sheet
A201®-2017 General Conditions of the Contract for Construction
Interested in getting unlimited access to our full 250+ library of agreements and forms? Visit the link below to learn more:
https://shop.aiacontracts.com/unlimited-subscription
March 15, 2022
A Schedule of Values (SOV) is an essential document in construction project management. It provides a breakdown of the total contract sum allocated to different portions of the contractor’s work, and it’s often required in the early stages of a project. But what exactly is an SOV, and why is it so important for both contractors and project owners?
In this guide, we’ll explain what a Schedule of Values is, why it’s required, and how it helps manage the financial aspects of a construction project.
A Schedule of Values is a document that supports the payment application process in construction projects. It allocates the Contract Sum (the total amount paid to the contractor) across different sections of the contractor’s work, as outlined in the project’s construction schedule. This document typically takes the form of a table with the following columns:
It might also include columns for retainage (amount withheld for quality assurance) and authorized adjustments.
This breakdown helps project managers, contractors, and owners track the project’s financial progress and ensure timely payments.
Creating a Schedule of Values (SOV) is a crucial task that ensures accurate payment applications and proper project oversight. Here’s a step-by-step guide on how to prepare one:
The American Institute of Architects (AIA) provides standardized forms that help contractors and architects manage project payments efficiently. Two key documents are often used:
A Schedule of Values is more than just a document for payment applications; it’s a critical project management tool. Here’s why contractors need an SOV:
As work progresses on a construction project, contractors must submit monthly payment applications that align with the Schedule of Values. These applications will include:
Changes to the Schedule of Values must be submitted to the architect with appropriate justification to maintain accuracy.
Changes to the schedule of values may occur if there are scope adjustments, change orders, or other project modifications. These updates must be submitted to the architect with supporting data to substantiate the changes.
The level of detail required depends on the project’s complexity, but the more detailed and transparent the SOV, the less likely there will be confusion about payments. Generally, it should include both major work sections and specific tasks or materials where possible.
A well-maintained Schedule of Values provides valuable insights into the progress of a construction project. It not only helps contractors manage cash flow and payments but also enables project owners and architects to monitor project performance and ensure the budget is being adhered to.
In summary, a Schedule of Values is a fundamental component of construction project management. It serves as the basis for payment applications, helps contractors manage cash flow, and provides transparency for all parties involved. Whether you’re a contractor, project manager, or owner, understanding and creating an accurate Schedule of Values will ensure your project runs smoothly and payments are made on time.
AIA Contract Documents has provided this article for general informational purposes only. The information provided is not legal opinion or legal advice and does not create an attorney-client relationship of any kind. This article is also not intended to provide guidance as to how project parties should interpret their specific contracts or resolve contract disputes, as those decisions will need to be made in consultation with legal counsel, insurance counsel, and other professionals, and based upon a multitude of factors.