How To Ensure Your Contract Workflow Reflects California’s Private Works Retainage Cap

California changed its private-project retainage rules this year. For contracts entered into on or after Jan. 1, 2026, Senate Bill 61 generally limits retention to 5%. The change affects payment terms and workflows from the owner-contractor agreement through lower-tier subcontracts.

SB 61 Limits Retainage on Private Works

SB 61 was passed in 2025 and took effect as Civil Code section 8811 on Jan. 1, 2026. It applies to private works of improvement entered into on or after that date. The statute limits retainage to 5% of each payment and 5% of the contract price.

Lower-tier retainage also can’t exceed the percentage set in the owner-contractor agreement. That rule matters when a prime contract uses less than 5%. A contractor or subcontractor cannot automatically withhold the full statutory maximum downstream when the upstream percentage is lower.

Does the 5% Cap Apply to Every Project?

No. The law doesn’t apply to a residential project that’s not mixed-use and does not exceed four stories. It also provides an exception for situations where performance and payment bonds were requested but not provided.

If the new retainage limit is violated and a party files suit to enforce it, the court must award reasonable attorney fees to the prevailing party. That fee provision gives owners, contractors, and subcontractors a practical reason to confirm the correct percentage before withholding retainage.

Pro Tip Confirm the project type, any exceptions, and the governing contract date before making any changes. The 5% cap doesn’t apply to every project or subcontract.

Key Takeaway: What To Update in Your Contract and Payment Workflow

The first step is to align contract language and project workflows with the new statutory requirements, if applicable. California private-project teams should review:

  • Retainage percentages in prime contracts and subcontracts
  • Payment application terms and schedules of values
  • Bond requirements and bid-stage notices
  • Accounting controls for total retainage across the contract price

In addition, payment forms and schedules of values should reflect the applicable percentage, and project accounting systems should match those documents.

Owners should create a claim calendar that reaches legal, finance, and project personnel as soon as a qualifying demand arrives. Contractors should preserve mailing records, account for disputed and undisputed amounts, and track the two-step work suspension notice. Subcontractors should understand and mirror the upstream process so pass-through claims and retention requirements don’t create avoidable gaps.

Keep Retainage Terms Coordinated

Retainage is only one part of payment administration. AIA Contract Documents (ACD) forms can help keep the contract sum, completed work, change orders, prior payments, and current retainage in one consistent record. Review the payment application process before the next billing cycle and obtain project-specific legal guidance when coverage or an exception is uncertain.

Disclaimer: The information contained in this article is for general informational purposes only, and the views contained herein are the author’s own. It is not legal advice or legal opinion; it does not create any attorney-client relationship; and it may not be used to indicate any intent or to inform any interpretation of ACD’s documents or services, which the AIA Documents Committee separately creates. If you need advice, seek the help of an attorney or other qualified professional who can help you make decisions based on the specifics of your situation.