How Liquidated Damages in Construction Can Cap What Owners Recover

Liquidated damages give owners and contractors a predictable number for late completion. That certainty is the point. But when the contract makes liquidated damages (LDs) the only remedy for delay, that number can become a ceiling or constraint, even after a contractor defaults.

A recent New York appellate decision shows how that ceiling carried over to the contractor’s surety. It also shows how a single change order settled how LDs would be counted across three buildings.

A Default on a Three-Building Project

In Thorobird Grand LLC v. M. Melnick & Co., the owners hired M. Melnick & Co. as general contractor to build three buildings in the Bronx located at three separate addresses. Federal Insurance Co. issued a performance bond for the project.

In 2019, the owners became unsatisfied with Melnick’s performance and ultimately declared the contractor in default, terminating the contract. Because there was a performance bond in place, Thorobird called on the surety, Federal Insurance Co., to step in. The surety chose to complete the work itself (via a replacement contractor) and signed a takeover agreement with the owners, effectively stepping into the contractor’s shoes and arranging for the completion of the project.

The owners then sued both companies. They wanted liquidated damages calculated separately for each building, plus their actual and consequential delay costs.

How the Courts Limited the Owners’ Delay Recovery

The contractor and surety each asked the lower court to dismiss parts of the claims before trial. The lower court agreed in part, throwing out the per-building liquidated damages claims and the claim for actual and consequential delay damages under the takeover agreement. The owners appealed.

The appellate court unanimously affirmed, for three reasons:

  • Liquidated damages were the exclusive remedy. The construction contract expressly limited delay damages to LDs, so actual and consequential delay damages weren’t available.
  • The surety owed no more than the contractor. Once the surety elected to complete the work, the bond made its responsibilities no greater than the contractor’s. The takeover agreement couldn’t expand that.
  • Liquidated damages ran on a project basis. The contract applied LDs for each day the “entire” work was late. A 2018 change order confirmed that LDs would be assessed “on a project basis and not a per building basis.”

Key Takeaways for Owners and Contractors

It’s important to decide whether liquidated damages will be exclusive. If an owner wants the option to recover actual delay costs after a default, the contract should clearly say so. In the A101® – Agreement Between Owner and Contractor, Section 4.5 is where the parties set LDs.

Address phased and multi-building work. State whether LDs run per building, per phase, or project-wide, and how they interact. In this case, there’s a massive difference between liquidated damages being calculated for the project as a whole or for each of the 3 contracted buildings.

Treat change orders as contract amendments (because they are). Here, a change order quietly decided the damages question well before the issue at hand. Review any LD language in a G701® – Change Order as carefully as the base agreement.

Read the bond with the contract. The A312® – Performance Bond includes similar language: when the surety acts on a default under certain options, its responsibilities to the owner are no greater than the contractor’s.

Pro Tip Compare the daily LD rate to realistic delay costs, such as financing, lost rent, and extended fees. If LDs are the only delay remedy, the rate needs to reflect your true exposure.

As always, it’s a good idea to have a construction lawyer review liquidated damages and bond terms before you sign.

Set Liquidated Damages That Work

Clear LD terms help owners, contractors, and sureties understand the cost of delay before work begins.

Disclaimer: The information contained in this article is for general informational purposes only, and the views contained herein are the author’s own. It is not legal advice or legal opinion; it does not create any attorney-client relationship; and it may not be used to indicate any intent or to inform any interpretation of ACD’s documents or services, which the AIA Documents Committee separately creates. If you need advice, seek the help of an attorney or other qualified professional who can help you make decisions based on the specifics of your situation.